Translations:GanttScheduler Ändringshistorik/1/en
Från DataPolarna
V3.0.45 2015-12-08
- Inactive delay causes and machines will not appear in the program.
- You can view messages as tooltip. Setting is required.
- In the File / Preferences.
- For each ganttview showing messages.
- During sequential manner Show hint about to "true".
- During info text and check "Show hint".
- Work order, the previous activity is shown when it ends exactly at the same time as the next start.
- Resources can be set up so that they do not show location messages that neither has activity type nor resource group.
- The setting is in the Tools / Manage / Manage activity types and resources.
- The setting is located on each resource and is called "View generic place messages".
- Comment requirement for extra activities is configurable. This setting is found under Tools / Preferences and is called "Comments must be reported for extra activities."
- Rep orted activities shown at the exact recorded time, regardless of schedule.
- Moving activities and the push feature use schedule.
- If you want an activity outside the schedule, you can hold down Alt while moving it.
- Press and hold down shift if you want to move, rather than extend it when the activity is small.
- The requirement to hold down alt when you extend an activity is removed.
- You can change the shift schedule on several activities at a time.
- You can mark messages as important. Messages will then be printed on all work orders whether they belong to the place or not.
- Paste fill and waste rock fill is available in stope properties.
- Tons including waste dilution is used in stope properties.
- Dynamic capacity can be used in length formulas.
- When reporting loading a check box "Full" is available, if you check it then the capacity of the re-muck bay is adjusted to its content.
- The activities function under Tools / Options in the check box "Report destination is filled".