Translations:GanttScheduler Ändringshistorik/1/en

Från DataPolarna
Version från den 7 mars 2016 kl. 09.30 av Andersk (Diskussion | bidrag) (Skapade sidan med '== V3.0.45 2015-12-08 == * Inactive delay causes and machines will not appear in the program. * You can view messages as tooltip. Setting is required. ** In the File / Prefere...')

(skillnad) ← Äldre version | Nuvarande version (skillnad) | Nyare version → (skillnad)
Hoppa till: navigering, sök

V3.0.45 2015-12-08

  • Inactive delay causes and machines will not appear in the program.
  • You can view messages as tooltip. Setting is required.
    • In the File / Preferences.
    • For each ganttview showing messages.
    • During sequential manner Show hint about to "true".
    • During info text and check "Show hint".
  • Work order, the previous activity is shown when it ends exactly at the same time as the next start.
  • Resources can be set up so that they do not show location messages that neither has activity type nor resource group.
    • The setting is in the Tools / Manage / Manage activity types and resources.
    • The setting is located on each resource and is called "View generic place messages".
  • Comment requirement for extra activities is configurable. This setting is found under Tools / Preferences and is called "Comments must be reported for extra activities."
  • Rep orted activities shown at the exact recorded time, regardless of schedule.
    • Moving activities and the push feature use schedule.
    • If you want an activity outside the schedule, you can hold down Alt while moving it.
    • Press and hold down shift if you want to move, rather than extend it when the activity is small.
    • The requirement to hold down alt when you extend an activity is removed.
  • You can change the shift schedule on several activities at a time.
  • You can mark messages as important. Messages will then be printed on all work orders whether they belong to the place or not.
  • Paste fill and waste rock fill is available in stope properties.
  • Tons including waste dilution is used in stope properties.
  • Dynamic capacity can be used in length formulas.
  • When reporting loading a check box "Full" is available, if you check it then the capacity of the re-muck bay is adjusted to its content.
    • The activities function under Tools / Options in the check box "Report destination is filled".